Tanzania's overall standard-gauge rail program is divided into five sections, called lots. Map courtesy of Yapi Merkezi

 

Turkish contractor Yapi Merkezi late last month signed a $1.9-billion turnkey contract for the construction of 368 kilometers of electrified standard gauge railway (SGR) in Tanzania comprising all infrastructure works and the materials and systems for the trackwork, catenary power supply, signaling and telecommunications.

This is the third construction contract for the firm, which holds two other contracts for the overall SGR project—the 300-km Phase One connecting East Africa’s second biggest port of Dar es Salaam to Morogoro and the 426-km. Phase Two linking Morogoro to Makutupora. Phase 3 of the railway line is the third of five in the construction of a 1,219-km line linking Tanzania to neighboring countries, including Rwanda, Burundi and Uganda. “We are expecting to commence construction within the first quarter of 2022,” said Başar Arıoğlu, chairman of Yapı Merkezi Construction and Industry, the flagship of the Yapi Merkezi Group and Yapı Merkezi Holding.

This portion of the SGR line links Makutupora and Tabora with seven stations at Manyoni, Itigi, Tura, Malongwe, Goweko, Igalula and Tabora. The SGR trains will travel as high as160km/hr.

“Decorative elements obtained from Tanzania’s rich and colorful culture will be reflected in the design of station exteriors and interiors. Such cultural elements will also be used in visible sections of the line, such as viaducts and bridges,” says Arıoğlu.

The line, which will be constructed over a 46-month period, will increase Tanzania’s total investment in the SGR network to $6.3 billion.

Basar says the SGR line will handle higher axle loads and faster speeds and significantly increase the transportation capacity along the alignment, resulting in reduced costs for cargo and faster and comfortable rides for passengers.

“Most importantly, reduced carbon emissions will protect the world-renowned natural treasures of Tanzania and as a continuation of the previous two lots of the SGR, cargo trains will help decongest of the port of Dar es Salaam by ensuring goods that arrive at the port are moved towards destinations inland without delays and with ease,” he added.

Tanzania President Samia Suluhu Hassan has stated that her government is unable to finance the huge railway project using domestically generated revenues, and is pushing for concessional loans to finance a total of 2561 km of the SGR network concurrently with the improvement of the existing meter gauge line, which is narrower. Both lines are running parallel to each other.

Arıoğlu says the third phase passes through a terrain that is “mainly characterized by smooth topography, excluding the portion from Makutupora to Manyoni with two steep climbing sections with a total length of 30 kilometers.”

“One of the biggest challenges is the unknown regarding the actual topography and geotechnical conditions of the route, which were not fully available to the contractor at the tendering stage,” he adds.

Planning of the drainage and movement of water around the new line is a major engineering challenge and an important factor for the safe operation and durability of the SGR system, Basar notes. “The progress of the works could be affected by such activities as relocations and expropriations that must be carried out according to the principles set out in Environmental and Social Action Plans." - Shem Oirere, 

Turkish contractor Yapi Merkezi late last month signed a $1.9-billion turnkey contract for the construction of 368 kilometers of electrified standard gauge railway (SGR) in Tanzania comprising all infrastructure works and the materials and systems for the trackwork, catenary power supply, signaling and telecommunications.

This is the third construction contract for the firm, which holds two other contracts for the overall SGR project—the 300-km Phase One connecting East Africa’s second biggest port of Dar es Salaam to Morogoro and the 426-km. Phase Two linking Morogoro to Makutupora. Phase 3 of the railway line is the third of five in the construction of a 1,219-km line linking Tanzania to neighboring countries, including Rwanda, Burundi and Uganda. “We are expecting to commence construction within the first quarter of 2022,” said Başar Arıoğlu, chairman of Yapı Merkezi Construction and Industry, the flagship of the Yapi Merkezi Group and Yapı Merkezi Holding.

This portion of the SGR line links Makutupora and Tabora with seven stations at Manyoni, Itigi, Tura, Malongwe, Goweko, Igalula and Tabora. The SGR trains will travel as high as160km/hr.

“Decorative elements obtained from Tanzania’s rich and colorful culture will be reflected in the design of station exteriors and interiors. Such cultural elements will also be used in visible sections of the line, such as viaducts and bridges,” says Arıoğlu.

The line, which will be constructed over a 46-month period, will increase Tanzania’s total investment in the SGR network to $6.3 billion.

Basar says the SGR line will handle higher axle loads and faster speeds and significantly increase the transportation capacity along the alignment, resulting in reduced costs for cargo and faster and comfortable rides for passengers.

“Most importantly, reduced carbon emissions will protect the world-renowned natural treasures of Tanzania and as a continuation of the previous two lots of the SGR, cargo trains will help decongest of the port of Dar es Salaam by ensuring goods that arrive at the port are moved towards destinations inland without delays and with ease,” he added.

Tanzania President Samia Suluhu Hassan has stated that her government is unable to finance the huge railway project using domestically generated revenues, and is pushing for concessional loans to finance a total of 2561 km of the SGR network concurrently with the improvement of the existing meter gauge line, which is narrower. Both lines are running parallel to each other.

Arıoğlu says the third phase passes through a terrain that is “mainly characterized by smooth topography, excluding the portion from Makutupora to Manyoni with two steep climbing sections with a total length of 30 kilometers.”

“One of the biggest challenges is the unknown regarding the actual topography and geotechnical conditions of the route, which were not fully available to the contractor at the tendering stage,” he adds.

Planning of the drainage and movement of water around the new line is a major engineering challenge and an important factor for the safe operation and durability of the SGR system, Basar notes. “The progress of the works could be affected by such activities as relocations and expropriations that must be carried out according to the principles set out in Environmental and Social Action Plans." - Shem Oirere, Engineering News-Record

About IEA Media Ltd

Informer East Africa is a UK based diaspora Newspaper. It is a unique platform connecting East Africans at home and abroad through news dissemination. It is a forum to learn together, grow together and get entertained at the same time.

To advertise events or products, get in touch by info [at] informereastafrica [dot] com or call +447957636854.
If you have an issue or a story, get in touch with the editor through editor[at] informereastafrica [dot] com or call +447886544135.

We also accept donations from our supporters. Please click on "donate". Your donations will go along way in supporting the newspaper.

Get in touch

Our Offices

London, UK
+44 7886 544135
editor (@) informereastafrica.com
Slough, UK
+44 7957 636854
info (@) informereastafrica.com

Latest News

Israel’s Netanyahu, Gallant issued ICC arrest warrants: What’s next?

Israel’s Netanyahu,...

This is the first time there has been an indictment for Netanyahu since Israel’s war on Gaza began...

Protecting at-risk populations from mpox in the Democratic Republic of the Congo

Protecting at-risk p...

World Health Organization (WHO) is working closely with national health authorities to implement ta...

Mali military administration appoints Gen. Abdoulaye Maiga new premier

Mali military admini...

Appointment comes after military administration dismissed civilian Premier Choguel Kokalla Maiga ove...

Ruto cancels Adani's infrastructure deals after bribery allegations

Ruto cancels Adani&#...

President William Ruto.[Elvis Ogina, Standard] President William Ruto has cancelled the controversi...

For Advertisement

Big Reach

Informer East Africa is one platform for all people. It is a platform where you find so many professionals under one umbrella serving the African communities together.

Very Flexible

We exist to inform you, hear from you and connect you with what is happening around you. We do this professionally and timely as we endeavour to capture all that you should never miss. Informer East Africa is simply news for right now and the future.

Quality News

We only bring to you news that is verified, checked and follows strict journalistic guidelines and standards. We believe in 1. Objective coverage, 2. Impartiality and 3. Fair play.

Banner & Video Ads

A banner & video advertisement from our sponsors will show up every once in a while. It keeps us and our writers coffee replenished.